Home/Business/Anderson Ltd absorbs overheads on a direct labour hours basis, the following information is available: Total budgeted manufacturing overhead: £299,250 Direct materials consumption per unit: 1.5kg Material price per kg: £3.00 Direct labour hours per unit: 3 1/2 Labour cost per hour: £7.50 Total budgeted production level: 9,000 units What is the indirect overhead absorption rate on the basis that Anderson currently adopts? £9.50 per labour hour £9.25 per labour hour £9.00 per labour hour £10.50 per labour hour
Question
Solved1 AnswerAnderson Ltd absorbs overheads on a direct labour hours basis, the following information is available: Total budgeted manufacturing overhead: £299,250 Direct materials consumption per unit: 1.5kg Material price per kg: £3.00 Direct labour hours per unit: 3 1/2 Labour cost per hour: £7.50 Total budgeted production level: 9,000 units What is the indirect overhead absorption rate on the basis that Anderson currently adopts? £9.50 per labour hour £9.25 per labour hour £9.00 per labour hour £10.50 per labour hour
ADTRL3The Asker · Accounting
Transcribed Image Text: Anderson Ltd absorbs overheads on a direct labour hours basis, the following information is available: Total budgeted manufacturing overhead: £299,250 Direct materials consumption per unit: 1.5kg Material price per kg: £3.00 Direct labour hours per unit: 3 1/2 Labour cost per hour: £7.50 Total budgeted production level: 9,000 units What is the indirect overhead absorption rate on the basis that Anderson currently adopts? £9.50 per labour hour £9.25 per labour hour £9.00 per labour hour £10.50 per labour hour
More
Transcribed Image Text: Anderson Ltd absorbs overheads on a direct labour hours basis, the following information is available: Total budgeted manufacturing overhead: £299,250 Direct materials consumption per unit: 1.5kg Material price per kg: £3.00 Direct labour hours per unit: 3 1/2 Labour cost per hour: £7.50 Total budgeted production level: 9,000 units What is the indirect overhead absorption rate on the basis that Anderson currently adopts? £9.50 per labour hour £9.25 per labour hour £9.00 per labour hour £10.50 per labour hour
See Answer
Add Answer +20 Points
Community Answer
C7IDN0
See all the answers with 1 Unlock Get 4 Free Unlocks by registration
false
Answer Option A is correct. Overhead absorption rate = budgeted overhead / budgeted labour cost = 299250 ÷ (3.5*7.5*9000) = ... See the full answer