Q.1) Following are three activities of project development process: - 1) Planning 2) Execution 3) Maintenance. Ans: Execution and maintenance. Q.2)  Following are uncertainty in activity duration on civil engineering projects. - Labor issue ( Eg labour strike, accident) - Weather ( Cyclone, earthquake etc) - Differing site conditions: Rain, hailstorm etc Rest two material availablity and project financial delay are not uncertainty. Ans : Material availability and project finance delay are not example of uncertainty in activity duration. ...