QUESTION

Text
Image


Question 46 1 Point Consider the following table of activities that describes a project network. What is the first activity you would crash? Activity Predecessors Normal duration (days) Crash duration (days) Normal cost Crash cost A - $53 \$ 1,000 \$ 4,000$ BA $85 \$ 4,000 \$ 7,000$ CA $74 \$ 2,000 \$ 4,000$ D B, C63\$1,000\$2,000 E B, C $95 \$ 5,000 \$ 8,000 \mathrm{FB}, \mathrm{C} 106 \$ 3,000 \$ 5,000 \mathrm{G}$ D, E, F $54 \$ 2,000 \$ 5,000$ (A) A (B) 8 (C) $D$ (D) $\mathrm{F}$ (E) $\mathrm{G}$

Public Answer

983XRJ The First Answerer