Question QUESTION: Hanna Ltd. has the following information available for March: Total Total Budget Actual Units 2,500 2,800 Direct materials $8,125 $8,540 Direct labour $32,000 $36,680 Variable overhead $55,000 $60,200 Fixed overhead $77,500 $92,400 Prepare a flexible budget at the actual output level and use the information to answer the following questions. What is the total direct materials cost on the flexible budget? What is the total direct labour costs on the flexible budget? A/ What is the total variable overhead costs on the flexible budget? A/ Previous Page What is the total fixed overhead costs on the flexible budget? Next Page A/ What is the total production costs on the flexible budget? A/ A/ Page 1 of 2

HAFK2N The Asker · Other Business

Transcribed Image Text: QUESTION: Hanna Ltd. has the following information available for March: Total Total Budget Actual Units 2,500 2,800 Direct materials $8,125 $8,540 Direct labour $32,000 $36,680 Variable overhead $55,000 $60,200 Fixed overhead $77,500 $92,400 Prepare a flexible budget at the actual output level and use the information to answer the following questions. What is the total direct materials cost on the flexible budget? What is the total direct labour costs on the flexible budget? A/ What is the total variable overhead costs on the flexible budget? A/ Previous Page What is the total fixed overhead costs on the flexible budget? Next Page A/ What is the total production costs on the flexible budget? A/ A/ Page 1 of 2
More
Transcribed Image Text: QUESTION: Hanna Ltd. has the following information available for March: Total Total Budget Actual Units 2,500 2,800 Direct materials $8,125 $8,540 Direct labour $32,000 $36,680 Variable overhead $55,000 $60,200 Fixed overhead $77,500 $92,400 Prepare a flexible budget at the actual output level and use the information to answer the following questions. What is the total direct materials cost on the flexible budget? What is the total direct labour costs on the flexible budget? A/ What is the total variable overhead costs on the flexible budget? A/ Previous Page What is the total fixed overhead costs on the flexible budget? Next Page A/ What is the total production costs on the flexible budget? A/ A/ Page 1 of 2
Community Answer
DQMGT9

As per given details please refer below answer :- Need to use the actual unit output and budgeted rate per unit. First need to calculate budgeted rate per unit. Cost per unit = Budgeted Cost / Budgeted units   Description Budgeted Units Budgeted Cost Cost per unit Direct Material                      2,500  $                8,125  $              3.25 Direct Labor                      2,500  $             32,000  $            12.80 Variable Overhead                      2,500  $             55,000  $            22.00 Fixed Overhead                      2,500  $             77,500  $   &#1 ... See the full answer