Question Task A. High level analysis B. Selection of hardware platform C. Installation and commissioning of hardware D. Detailed analysis of core modules E. Detailed analysis of supporting modules Duration Predecessor 1 week 1 day 2 weeks B 2 weeks A 2 weeksD 2 weeks D 3 weeks E 1 week F I week 1 day F. Programming of core modules G. Programming of supporting modules H. Quality assurance of core modules I. Quality assurance of supporting modules J.Core module training C.H K. Development and QA of accounting reporting L. Development and QA of management reporting M. Development of Management Information System I week N. Detailed training I week 1 week L I week I. J. K. M Describe the Project. predecessor activity. Create a Table like all of the ones above with all of the activities Create a Network Diagram a. b. c. d. Calculate ES, EF, LS, LF Define the Critical Path How many weeks will the project take to complete?

TEMTFK The Asker · Computer Science

Transcribed Image Text: Task A. High level analysis B. Selection of hardware platform C. Installation and commissioning of hardware D. Detailed analysis of core modules E. Detailed analysis of supporting modules Duration Predecessor 1 week 1 day 2 weeks B 2 weeks A 2 weeksD 2 weeks D 3 weeks E 1 week F I week 1 day F. Programming of core modules G. Programming of supporting modules H. Quality assurance of core modules I. Quality assurance of supporting modules J.Core module training C.H K. Development and QA of accounting reporting L. Development and QA of management reporting M. Development of Management Information System I week N. Detailed training I week 1 week L I week I. J. K. M Describe the Project. predecessor activity. Create a Table like all of the ones above with all of the activities Create a Network Diagram a. b. c. d. Calculate ES, EF, LS, LF Define the Critical Path How many weeks will the project take to complete?
More
Transcribed Image Text: Task A. High level analysis B. Selection of hardware platform C. Installation and commissioning of hardware D. Detailed analysis of core modules E. Detailed analysis of supporting modules Duration Predecessor 1 week 1 day 2 weeks B 2 weeks A 2 weeksD 2 weeks D 3 weeks E 1 week F I week 1 day F. Programming of core modules G. Programming of supporting modules H. Quality assurance of core modules I. Quality assurance of supporting modules J.Core module training C.H K. Development and QA of accounting reporting L. Development and QA of management reporting M. Development of Management Information System I week N. Detailed training I week 1 week L I week I. J. K. M Describe the Project. predecessor activity. Create a Table like all of the ones above with all of the activities Create a Network Diagram a. b. c. d. Calculate ES, EF, LS, LF Define the Critical Path How many weeks will the project take to complete?
Community Answer
Y0MEIN

The project scenario for the activities can be described asbelow:a. Table of Activities, time taken and it's predecessorrelationships.To make it simple take all the times in days. So, it wouldbe:b. The Network Diagram. There a just a few simple steps to befollowed.1. Each activity should have two events. The one at thebeginning is called the tail and the other is called the head2. The network diagram should have an unique tail event and anunique head event3. Each arrow should only consist of one activity4. In the cases of precedence relationship, we create a dummyactivity (as the name itself tells it is dummy there is no time orduration for thi ... See the full answer