The following table gives the activities for buying a new car. Construct the project network and find the critical path, inclicate clearly the critical activites and the makespan of the project Activity Predecessor(s) Duration (days) 3 14 A 1 3 A: Feasibility study B:F'ind potential buyer for present car C:List possible models D:Research all possible models E:Conduct interview with mechanic F:Collect dealer propaganda G-Compile pertinent data H:Choose top three models I: Test-drive all three choices 1 2 D.E.F 1 G 1 H 3 J:Gather warranty and financing data H1 2 K:Choose one car 1,J 2 L:Choose dealer K 2 4 M:Search for desired color and options L N:Text-drive model once again L 0:Purchase new car B.MN 1 3 ...